Enel Green Power España connects four wind farms in Zaragoza, with an investment of €100 million

  • The El Campo, La Estanca, Loma Gorda and Santo Domingo de Luna plants have a total capacity of 98 MW and can generate 360 GWh per year.
  • The development of these plants is in response to Endesa's strategy of reaching 10.2 GW of renewable installed capacity by 2022, investing €3.8 billion to achieve an emissions-free generation mix by 2050.

Enel Green Power España (EGPE), Endesa's renewable energy subsidiary, has connected the El Campo, La Estanca, Loma Gorda and Santo Domingo de Luna wind farms to the grid. Together, these four wind farms have a total capacity of 98 MW and have involved a capital expenditure of €100 million.

They are located in the province of Zaragoza and with them the number of the company’s wind farms commissioned in the region of Aragon in recent weeks, following the Sierra Costera I (Teruel) and Campoliva I, Campoliva II and Primoral plants (Zaragoza), rises to eight.

José Bogas, CEO of Endesa, said that “Endesa is already finishing up grid connection of the 879 renewable MW awarded in the 2017 auction, which demonstrates the company's determination to meet the commitments it acquired in the tender called by the government. This represents a major step forward in Endesa's commitment to clean energy production, which is one of the cornerstones of Spain’s energy transition policy.”

EGPE was awarded 540 MW of wind power and 339 MW of solar energy in the government auctions held in May 2017, which entail a total investment of more than €800 million. The company has so far connected 339 solar MW and some 285 wind MW to the grid and is completing the construction and connection of the remaining wind projects, which will be ready by the end of the year.

The El Campo wind farm, composed of six turbines, will be able to generate 75 GWh a year, enough energy to supply 19,100 families. Its coming on stream will prevent the emission of more than 49,000 metric tons of CO 2 annually into the atmosphere. It straddles the boundary between the municipalities of Mallén and Fréscano, in the province of Zaragoza. Work for its construction began on 21 January 2019 and ended on 21 November. It was connected to the grid on 13 December.

The La Estanca wind farm consists of eight wind turbines that provide a total capacity of 24 MW. It will produce 97 GWh per year, enough to supply energy to some 24,500 families and will prevent the annual emission of some 63,500 metric tons of CO 2 into the atmosphere. Its construction began on 25 March 2019 and ended on 21 November 2019. It was connected to the grid on 13 December. A total of 51% of this wind farm is held by Enel Green Power España and 49% by Bancale Servicios Integrales S.L. It is located in the municipalities of Mallén and Fréscano in the province of Zaragoza.

The Loma Gorda wind farm, consisting of seven turbines, will be able to generate 70 GWh a year, enough energy to supply 17,800 families. Its coming on stream will prevent the emission of more than 46,000 metric tons of CO 2 annually into the atmosphere. It is located in Fuendetodos, Zaragoza. Ground was broken on 5 October 2018 and ended on 31 October 2019. It was connected to the grid on 29 November 2019.

The Santo Domingo de Luna wind farm has a capacity of 30 MW and nine wind turbines. It will produce 116 GWh per year, enough to supply 29,500 households, and prevent the annual emission of 76,000 metric tons of CO2 into the atmosphere. Its construction began on 20 November 2018 and ended on 27 September 2019. It was connected to the grid on 18 November. It is located in the municipalities of Luna, Las Pedrosas and Sierra de Luna in the province of Zaragoza. Enel Green Power España, with 51%, and General Eólica Aragonesa, with the remaining 49% are the plant's shareholders.

During the construction of these wind farms, Enel Green Power's "Sustainable Construction Site" model was applied. This included the installation of photovoltaic panels to cover part of power needs during construction. Water saving measures were also adopted by installing rain collection systems and tanks. Once construction is finished, both the photovoltaic panels and the water saving equipment will be donated for public use. The construction of these wind farms has contributed to partially funding an Industrial Development Plan in the area.

The construction of this renewable capacity is in line with Endesa's strategy of completely decarbonising its generation mix by 2050. According to the company’s latest Strategic Plan the next milestone is to reach 10.2 GW of renewable installed capacity by 2022, compared with the estimated 7.4 GW by the end of 2019, with a total investment of some €3.8 billion.

Endesa has followed a facility development model that encompasses actions to create social value for the environments in which they are built, the so-called Creating Shared Value (CSV) model. Among these actions, priority was given for these four projects to the incorporation of local labour, as well as hiring catering services and workers' accommodation locally.

In the case of Santo Domingo de Luna and Loma Gorda specifically, some of the notable actions undertaken, worth more than €184,000 and €117,000 respectively, included the promotion of electric mobility for transfers in construction jobs by installing a charging point and using electric vehicles. In the case of El Campo and La Estanca, with CSV actions worth more than €190,000, energy efficiency actions, such as efficient lighting projects by replacing with LED technology and promoting self-consumption, were carried out in five of the municipalities in the area.

Endesa currently manages more than 7,176 MW of renewable capacity in Spain. Of this figure, 4,701 MW are from conventional hydraulic generation. The rest, more than 2,468 MW, are managed through EGPE and come from wind (2,036 MW), solar (339 MW), mini-hydro (79 MW) and other renewable energy sources (14 MW).

Enel Green Power, the global renewable energy business line of the Enel Group, to which Endesa belongs, is dedicated to the development and operation of renewables worldwide, with a presence in Europe, America, Asia, Africa and Oceania. Enel Green Power is a global leader in the green energy sector with a managed capacity of about 46 GW in a generation combination that includes wind, solar, geothermal and hydroelectric energy and is at the forefront of the integration of innovative technologies in renewable energy power plants.

Documents

Press release in PDF

PDF (0.46MB) Download
advise icon go to the advise Facebook icon go to Facebook Twitter icon go to Twitter Youtube icon go to Youtube Messenger icon go to Messenger Linkedin icon go to Linkedin Instagram icon go to Instagram Shared Link icon Go to the shared link Checkmark Success icon Checkmark Success down arrow icon down arrow Previous Go to previous Next Go to the next close icon close add icon add up arrow icon up arrow oblique arrow icon look obliquely Arrow down icon Arrow down search engine icon search search engine icon search share icon share filter icon filter email icon send mail email icon email phone icon phone fax icon fac print icon print play icon play user icon go to the user section error icon an error has occurred info icon information thumb up icon like thumb up icon like thumb down icon don't like thumb down icon don't like clock icon Clock Lamp icon Lamp List icon List Map icon Go to the map Phone icon Phone Emergency icon Emergency Pause icon Pause Play icon Play Logout icon Sign off Phone icon Phone Download icon An icon representing a download Chat icon An icon representing a chat
go back icon go back in navigation number 50 icon go to product Tempo Happy 50 Horas calendar icon go to product Tempo Happy Día companies icon go to the business segment gas icon go to gas product catalog rising sun icon go to Tempo Verde-Renewable Energy product home icon go to the household segment 24 hours icon go to One Luz product electricity icon go to Luz's product catalog electricity and gas icon go to the Luz + Gas product catalog moon icon go to product One night light monkey wrench icon go to breakdowns and repairs sun icon go to Tempo Solar product clock icon go to Tempo Happy products 2 hour clock icon go to Tempo Happy 2 Hours product 24 hours icon go to product One Luz number 50 icon go to product Tempo Happy 50 Hours Medium Voltage power line See product catalog with electricity consumption from € 36,000 to € 360,000 / year High Voltage power line See catalog of products with electricity consumption more than € 360,000 / year company icon go to the business segment calendar icon go to product Tempo Happy Day Property management firms icon go to the Property management firms DarkSite icon DarkSite icon light bulb icon See product catalog with electricity consumption less than € 6,000 / year electricity and gas icon go to the Electricity+ Gas Products catalog electricity icon go to the electrical products catalog email icon email contact fax icon fax contact Low Pressure gas icon see catalog of gas products with consumption of less than € 6,000 / year High Pressure gas icon see catalog of gas products with consumption from € 6,000 to € 240,000 / year Medium Pressure gas icon see catalog of gas products with consumption of more than € 240,000 / year gas icon go to gas product catalog Enel icon go to the enel website heater icon heater maintenance service heater maintenance icon go to maintenance service OKGas Heater home icon go to the household segment pressure cooker icon pressure cooker monkey wrench icon go to breakdowns and repairs Medium Voltage power line icon see catalog of electricity products with consumption from € 6,000 to € 36,000 / year moon icon go to product One Night Light sphere icon go to personal website phone icon telephone contact rising sun icon go to Tempo Verde-Renewable Energy product solar panel icon go to photovoltaic solar energy clock icon go to Tempo Happy products black handyman icon with thumb down selected the reaction "I don't like it" little hand icon with thumb down select the reaction "I don't like it" black hand icon with thumb up selected the "like" reaction little hand icon with thumb up select the "like" reaction
Añadir otro equipo eléctrico Lorem ipsum dolor sit amet, consectetur adipisicing elit. Eliminar equipo eléctrico Lorem ipsum dolor sit amet, consectetur adipisicing elit. Aspiradora Lorem ipsum dolor sit amet, consectetur adipisicing elit. Horno Lorem ipsum dolor sit amet, consectetur adipisicing elit. Lavadora Lorem ipsum dolor sit amet, consectetur adipisicing elit. Lavavajillas Lorem ipsum dolor sit amet, consectetur adipisicing elit. Microondas Lorem ipsum dolor sit amet, consectetur adipisicing elit. Plancha Lorem ipsum dolor sit amet, consectetur adipisicing elit. Punto de recarga vehículo eléctrico Lorem ipsum dolor sit amet, consectetur adipisicing elit. Radiador eléctrico Lorem ipsum dolor sit amet, consectetur adipisicing elit. Secadora Lorem ipsum dolor sit amet, consectetur adipisicing elit. Split Aire Acondicionado Lorem ipsum dolor sit amet, consectetur adipisicing elit. Termo Lorem ipsum dolor sit amet, consectetur adipisicing elit. Tostador Lorem ipsum dolor sit amet, consectetur adipisicing elit. Vitrocerámica Lorem ipsum dolor sit amet, consectetur adipisicing elit. Power edit Lorem ipsum dolor sit amet, consectetur adipisicing elit. Map marker Lorem ipsum dolor sit amet, consectetur adipisicing elit.