Endesa will invest 2,655,000 euros in new interconnections of the Ibiza distribution network to advance towards the electrification of demand

Operators during the improvement works of the Ibiza distribution network.
  • A number of actions will be undertaken, including the installation of 14.3 km of overhead cable interconnections and the change of 3.95 km of underground network conductor.
  • The new interconnections will improve the operability of the network and progress towards the electrification of demand.

In 2022, Endesa, through its infrastructure and network subsidiary, e-distribución, will undertake the installation of new interconnections between lines and driver changes in Ibiza's medium voltage (15 kV) distribution network, with a view to making progress in the electrification of demand on the island of Ibiza with an investment of more than €2,655.000.

The most significant actions include the following:

  • Interconnection to LMT GERTRUDIS, with the installation of 4,290 metres of 15 kV overhead line.
  • A new underground interconnection for LMT PORTINATX with the installation of 2,539 metres of 15 kV underground line.
  • New interconnection of 3,015 metres between the LMT PORTINATX and LMT CARLOS lines to improve the quality of supply and the operability of the network between the municipalities of Sant Joan de Labritja and Santa Eulària des Riu.
  • Change of conductor for 1,897 meters of overhead line on the medium voltage LMT RIO de Santa Eulària des Riu line.

Investment for the actions on these infrastructures amounts to more than €2,655,000, of which €2,100,000 are for new interconnections and €555,000 for the change of underground line conductor, as well as making it easier to increase the electrification of demand, and it will improve the operability of the distribution network.

This investment will reduce the time the electricity supply is interrupted when there is a breakdown, so there will be an improvement to the quality of service for the entire area of influence for the installations that supply electricity on the island of Ibiza. It will be possible to put all these investments into action once the corresponding permits are available. They have already been requested from the administrations involved.

 

About Endesa

Endesa is the largest electricity company in Spain and the second largest in Portugal. The company is also the second largest gas operator in the Spanish market. Endesa operates an end-to-end business from generation and distribution to marketing and through Endesa X, also offers value-added services aimed at the decarbonisation of energy use in homes, companies, industries and Public Administrations. Endesa is firmly committed to the United Nations SDGs and strongly supports the development of renewable energies through Enel Green Power Spain, the digitalisation of grids through e-distribución, and Corporate Social Responsibility (CSR). The Endesa Foundation is also active in CSR. Our workforce numbers around 9,260 employees. Endesa is a division of Enel, Europe’s largest electricity group. 

Downloads

News in PDF

PDF (0.09MB) Download
advise icon go to the advise Facebook icon go to Facebook Twitter icon go to Twitter Youtube icon go to Youtube Messenger icon go to Messenger Linkedin icon go to Linkedin Instagram icon go to Instagram Shared Link icon Go to the shared link Checkmark Success icon Checkmark Success down arrow icon down arrow Previous Go to previous Next Go to the next close icon close add icon add up arrow icon up arrow oblique arrow icon look obliquely Arrow down icon Arrow down search engine icon search search engine icon search share icon share filter icon filter email icon send mail email icon email phone icon phone fax icon fac print icon print play icon play user icon go to the user section error icon an error has occurred info icon information thumb up icon like thumb up icon like thumb down icon don't like thumb down icon don't like clock icon Clock Lamp icon Lamp List icon List Map icon Go to the map Phone icon Phone Emergency icon Emergency Pause icon Pause Play icon Play Logout icon Sign off Phone icon Phone Download icon An icon representing a download Chat icon An icon representing a chat
go back icon go back in navigation number 50 icon go to product Tempo Happy 50 Horas calendar icon go to product Tempo Happy Día companies icon go to the business segment gas icon go to gas product catalog rising sun icon go to Tempo Verde-Renewable Energy product home icon go to the household segment 24 hours icon go to One Luz product electricity icon go to Luz's product catalog electricity and gas icon go to the Luz + Gas product catalog moon icon go to product One night light monkey wrench icon go to breakdowns and repairs sun icon go to Tempo Solar product clock icon go to Tempo Happy products 2 hour clock icon go to Tempo Happy 2 Hours product 24 hours icon go to product One Luz number 50 icon go to product Tempo Happy 50 Hours Medium Voltage power line See product catalog with electricity consumption from € 36,000 to € 360,000 / year High Voltage power line See catalog of products with electricity consumption more than € 360,000 / year company icon go to the business segment calendar icon go to product Tempo Happy Day Property management firms icon go to the Property management firms DarkSite icon DarkSite icon light bulb icon See product catalog with electricity consumption less than € 6,000 / year electricity and gas icon go to the Electricity+ Gas Products catalog electricity icon go to the electrical products catalog email icon email contact fax icon fax contact Low Pressure gas icon see catalog of gas products with consumption of less than € 6,000 / year High Pressure gas icon see catalog of gas products with consumption from € 6,000 to € 240,000 / year Medium Pressure gas icon see catalog of gas products with consumption of more than € 240,000 / year gas icon go to gas product catalog Enel icon go to the enel website heater icon heater maintenance service heater maintenance icon go to maintenance service OKGas Heater home icon go to the household segment pressure cooker icon pressure cooker monkey wrench icon go to breakdowns and repairs Medium Voltage power line icon see catalog of electricity products with consumption from € 6,000 to € 36,000 / year moon icon go to product One Night Light sphere icon go to personal website phone icon telephone contact rising sun icon go to Tempo Verde-Renewable Energy product solar panel icon go to photovoltaic solar energy clock icon go to Tempo Happy products black handyman icon with thumb down selected the reaction "I don't like it" little hand icon with thumb down select the reaction "I don't like it" black hand icon with thumb up selected the "like" reaction little hand icon with thumb up select the "like" reaction
Añadir otro equipo eléctrico Lorem ipsum dolor sit amet, consectetur adipisicing elit. Eliminar equipo eléctrico Lorem ipsum dolor sit amet, consectetur adipisicing elit. Aspiradora Lorem ipsum dolor sit amet, consectetur adipisicing elit. Horno Lorem ipsum dolor sit amet, consectetur adipisicing elit. Lavadora Lorem ipsum dolor sit amet, consectetur adipisicing elit. Lavavajillas Lorem ipsum dolor sit amet, consectetur adipisicing elit. Microondas Lorem ipsum dolor sit amet, consectetur adipisicing elit. Plancha Lorem ipsum dolor sit amet, consectetur adipisicing elit. Punto de recarga vehículo eléctrico Lorem ipsum dolor sit amet, consectetur adipisicing elit. Radiador eléctrico Lorem ipsum dolor sit amet, consectetur adipisicing elit. Secadora Lorem ipsum dolor sit amet, consectetur adipisicing elit. Split Aire Acondicionado Lorem ipsum dolor sit amet, consectetur adipisicing elit. Termo Lorem ipsum dolor sit amet, consectetur adipisicing elit. Tostador Lorem ipsum dolor sit amet, consectetur adipisicing elit. Vitrocerámica Lorem ipsum dolor sit amet, consectetur adipisicing elit. Power edit Lorem ipsum dolor sit amet, consectetur adipisicing elit. Map marker Lorem ipsum dolor sit amet, consectetur adipisicing elit.